Lusaka–Ndola Dual Carriageway Passes 90 Per Cent Mark, Full Completion Expected Early Next Year

Lusaka–Ndola Dual Carriageway Passes 90 Per Cent Mark, Full Completion Expected Early Next Year
Local News • Nov 18, 2026

Lusaka–Ndola Dual Carriageway Passes 90 Per Cent Mark, Full Completion Expected Early Next Year

Author

Breaking News Zambia

Local News

The US$650 million Lusaka–Ndola dual carriageway is more than 90 per cent complete, with full completion on schedule for early next year, Minister of Infrastructure and Urban Development Collins Nzovu said during a tour of the project. The project involves upgrading the…

The US$650 million Lusaka–Ndola dual carriageway is more than 90 per cent complete, with full completion on schedule for early next year, Minister of Infrastructure and Urban Development Collins Nzovu said during a tour of the project.

The project involves upgrading the Lusaka–Ndola Road into a modern dual carriageway and rehabilitating the 45-km Masangano–Fisenge–Luanshya Road, at a total investment of about US$650 million. The road concessionaire said completion is expected between April and May next year.

Mr Nzovu described the road as a “miracle project”, saying it was being delivered through a Public-Private Partnership (PPP) model by President Hakainde Hichilema’s administration at a time when the country was rebuilding its economy.

The minister said Government had inherited an infrastructure funding freeze from the Patriotic Front (PF), under which the country had defaulted on its debt obligations.

“We are coming from a situation where our economy was shrinking rather than growing. We are coming from a situation where the country was burdened by debt and all infrastructure projects were stopped and Government was not able to do any big project at all,” Mr Nzovu said.

He said seeing a road of more than 300 kilometres being successfully delivered under a PPP arrangement was a miracle, describing it as a model in Africa and saying nothing of this scale had happened before under the PPP arrangement.

“This road was in a dilapidated state 10 years ago, and now over 300 kilometres of road have been successfully completed under President Hichilema’s administration through the PPP model, which will now be replicated on the Lusaka–Livingstone and Sesheke dual carriageway, which we will soon embark on,” Mr Nzovu said.

“So, the PPP model is one President Hakainde Hichilema has encouraged us to use given the constrained fiscal space,” he added.

The minister said developing one of the country’s busiest economic corridors was aligned with the Grow Zambia Agenda, as it had greatly reduced congestion and road traffic accidents. With the expansion of the road, he said, motorists were pleased that transportation business had become more attractive, adding that the wheels of the economy were also moving at a faster rate.

Mr Nzovu said township roads would also be worked on under the PPP model, alongside the main roads. He announced the construction of modern markets along the stretch at Liteta in Chibombo District and at John Chinena, a development that pleased local residents.

In Kapiri Mposhi, however, the minister raised concern over the construction of structures on the road reserve, which he said could threaten future expansion. He warned local authorities against allocating plots within the lawfully designated road reserve, stating that those who put up structures risked losing them through demolition to make way for expansion. No private structure, he stressed, should be built within 50 metres of the road reserve.

He also cautioned goods transporters against overloading.

Project concessionaire Macro Ocean Investment Consortium’s assistant project manager Jane Kang said the 100 per cent completion mark would soon be reached.

In separate statements, Headman Liteta and John Chinena Market chairperson Prisca Mwansa thanked President Hichilema for the road and market infrastructure, which they said would promote business activities for local people.

Road Development Agency (RDA) director and chief executive officer Nelson Chuma said the project’s scope also included an additional 135 km of township roads to be worked on in Lusaka, Chibombo and Kabwe districts.

Mr Chuma said side lanes would also be constructed from the 70/70 area to the Mungule turn-off and at Zambeef Huntley Farm to accommodate large trucks, adding that the project was key to achieving the Grow Zambia Agenda. He, however, said the agency was concerned by encroachment within the lawfully cordoned 50-metre road reserve set aside for expansion.

Mr Nzovu, accompanied by RDA officers, is on a tour of road infrastructure in the Copperbelt and North-Western provinces, with the Lusaka–Ndola stretch on course for completion between April and May next year.