K67m Parliament Motel renovation project misses October deadline – Who is profiting from the delay & extended MP lodgings?

K67m Parliament Motel renovation project misses October deadline – Who is profiting from the delay & extended MP lodgings?
News • Nov 25, 2026

K67m Parliament Motel renovation project misses October deadline – Who is profiting from the delay & extended MP lodgings?

Author

Breaking News Zambia

News

Concerned taxpayers have questioned the delay in […]

Concerned taxpayers have questioned the delay in the completion of the renovation of Zambia’s Parliament Motel, considering how many months have passed since Government initially promised that the facility would be ready to accommodate Members of Parliament before the opening of the 14th National Assembly.

After the Zambian Business Times-ZBT received these concerns, it reviewed the project’s timelines and found that the K67 million renovation missed its original August 2026 deadline, while the revised end-of-October handover date has also passed without the facility being officially handed over.

In 2025, Infrastructure Minister Charles Milupi indicated that Parliament’s expansion works, including the chamber and motel, were expected to be completed before August 2026, but by August this year Permanent Secretary for Infrastructure Professor Albert Malama disclosed that the motel was only 30% complete.

Professor Malama subsequently indicated that the facility would be completed and handed over by the end of October 2026, but as of November 24, the deadline has passed by almost a month, with no public explanation provided for the continued delay.

The contractor has been identified as Eco Sense, although it has only been described as a local contractor, raising questions among taxpayers about its experience, the procurement process and who is responsible for ensuring that a K67 million public project is delivered on time.

The delay has also raised questions about accountability, particularly because the motel was reportedly only 30% complete in August, leaving 70% of the work unfinished with just two months remaining before the revised handover deadline.

Meanwhile, with 280 Members of Parliament having reported for duty following the opening of the 14th National Assembly on October 9, the public is demanding to know where lawmakers are currently staying and how much taxpayers are spending on their alternative accommodation.

Clerk of the National Assembly, Loveness Mayaka confirmed that renovations include the restaurant, kitchen, laundry, accessible rooms and other facilities, while Speaker Nelly Mutti has previously emphasised the need for Parliament to have suitable infrastructure rather than continue relying on rented premises.

However, no public breakdown has been provided on the interim accommodation arrangements or the cost of lodging lawmakers, leaving taxpayers questioning whether public funds are being used to pay for private hotels and lodges while Parliament’s own facility remains unfinished.

The accommodation arrangements have also prompted questions about possible conflicts of interest, with members of the public seeking clarification on whether any MPs or public officers are being accommodated in establishments owned by public officials and whether the relevant interests have been declared.

Another concern is the accommodation of the 40 Proportional Representation MPs, comprising 20 women, 15 youths and five persons with disabilities, especially because the renovation scope does not indicate the construction of more than 100 additional rooms to cater for the expanded membership.

The public is therefore demanding answers from the Ministry of Infrastructure and the National Assembly on why the deadlines were missed, what penalties apply to the contractor, where MPs are staying and how much the alternative arrangements are costing taxpayers, because the continued silence leaves a K67 million public project without clear accountability.

By Philip Sinkala